1. Introduction
This is a report on field visit to Sunkoshi Hydropower
station located at 81 km east from
Kathmandu in Sindhupalchowk district. The powerhouse was commissioned in
January 1972 with a friendly cooperation of the Water Conservancy and Electric
Power Ministry of the People’s Republic of China and Government of Nepal. The cost of the
project was approximately NRs. 109.37 million including transmission line up to
Kathmandu. The cumulative
generation of the station has reached 2,027.46 GWh in 2011/12 from the first
run. The station has generated 60.36 GWh in FY 2010/11 and 66.38 GWh in FY
2011/12 with an increase of 9.99%. The station has a share of 1.59% of the
total energy in the INPS in 2011/12.
2.
Objective
ü to know about the components of ROR hydropower project form intake
to powerhouse
ü to know how the components were laid and their working
ü to know about the threats to hydropower project like landslide
etc.
3. Salient features of Sunkoshi
Hydropower Plant
The salient features of sunkoshi
Hydropower station as obtained from the NEA website are :
Type
|
Run off River, Medium head plant
|
Location
|
Sindhupalchowk
|
Installed capacity
|
10.05MW
|
Annula design generation
|
70 GWh
|
River discharge
|
88 m3/s
|
Design discharge
|
39.9 m3/s
|
Maximum net head
|
30.5m
|
Length of canal
|
2.653 Km
|
Daily regulating pond capacity
|
67000 m3
|
Forebay capacity
|
18000 m3
|
Diameter of penstock
|
2.54m, 3 nos. with 13.3 m3/s
discharge in each
|
Turbine Generator set
|
3 nos.
|
Shaft configuration
|
Vertical
|
Turbine
|
Type : Francis (Model HL123a-LJ-140)
Output : 3530KW
Speed : 300 rpm
|
Generator
|
Type : Synchronous, 3 phase (Model : TS
325/36-20)
Capacity : 4000 KVA
Rated voltage : 6.3 KV, 50Hz
Rated current : 361 A
Rated power factor : 0.85
|
Transmission Line
|
66KV, Single circuit
|
Project Inception date
|
End of 1968
|
Project placed in service
|
January 1972
|
Project financed by
|
People’s Republic of China and Government of
Nepal
|
Project Cost
|
NRs. 109.37 million(including transmission
line)
|
4. Components of Sunkoshi Hydropower Plant
The Components of Sunkoshi hydropower
station visited are:
1. Dam
2. Intake
3. Headrace Canal
4. Settling basin
5. Spillway
6. Peaking pond
7. Forebay
8. Penstock
9. Power house
10. Tailrace canal
Each components are explained below :
4.1
Dam
The
dam of sunkoshi consists of six radial gates as outlet gate with hoist for
opening and closing of gates
when required. The dam increases the head, enough to divert the water towards intake. About 10% water are let pass
towards the downstream of river for as an environment
flow.
Radial
gate : It is most common and economical type of gate. The radial gate is operated
by rotating around its hinge about horizontal axis. Opening and closing of gate is controlled at
the hoist above it. While opening it occupies less space than that of
vertical gate.
Divide
wall : The divide wall is provided to prevent cross current i.e. for one directional flow.
Undersluice
: Undersluice gates are provided to flush the sediments downstream of
river.
4.2
Intake
It
is a hydraulic structure constructed to
withdraw required amount of discharge from river. There are 4
side intakes in sunkoshi hydropower station. At entry, trash rack has been provided to prevent
entry of logs, floating bodies, dead animals,
etc.
4.3 Headrace
Canal
A
canal is provided to convey the water from intake to forebay. A side canal has
also been provided which comes into
use during cleaning of settling basin. The length of canal is 2.653 Km.
4.4
Settling basin
The
settling basin is one of the most efficient devices for hydropower schemes, constructed on the head race canal for
removal of sediment load upto 0.2mm diameter particles
from flowing water which cannot be trapped by gravity trap.
The
settling basin of sunkoshi consists of enlarged section at entrance to reduce
the velocity and hence the
turbulence so that the bed load gets settled. Baffle walls are also provided to facilitate the reduction of
velocity. The settling basin is of hooper type. The section of the basin becomes converging into similar shape and
size of headrace canal at outlet.
Flushing
: When the sediments exceeds, deposited material tend to reduce X- sectional area of basin which
increases the velocity ultimately decreasing the trap efficiency.
So flushing should be done. In sunkoshi, three flushing gates are provided with hoist for gate operation
and flushing is continuous.
4.5
Spillway
To discharge
the excess water, overflow spillway of ogee shaped has been provided at downstream of settling basin.When water flows
over the crest of spillway, it must always
remain in contact with or slide over the surface of spillway. The spilled water
is mixed with the river through
the channel.
4.6
Peaking Pond
The peaking pond of the Sunkoshi Hydropower Plant is
utilized during the dry (winter) season
when very low sediment concentration exists in the river. During the wet (monsoon) season, the inlet gates of
the peaking ponds are closed to stop the access of sediment-loaded water. Since the peaking pond is located
just upstream of the forebay and
is only used during the dry season, the annual sediment deposition rate in the peaking pond is low.
4.7
Forebay
A
forebay or head pond is a temporary water storage, regulating reservoir
provided at downstream end of canal just at upstream of penstocks. At
instance when turbine rejects
the load, it acts as a storage reservoir whereas it supplies water as a sort of
regulating reservoir when load
increases.
In
sunkoshi, forebay has been provided just upstream of penstrock. A spillway has
also been provided at side of forebay
to spill the excess water. The water spilled is mixed into the river by dissipating its energy at stilling basin.
Flushing gate has also been provided
to flush the sediments of forebay.
Stoplogs
has also been provided. It is a gate used to prevent the flow through spillway or canal during the routine maintainence.
4.8
Penstock
Penstock is a pipe which carries water under pressure
from forebays to turbine installed in
powerhouse. Three penstock pipes has been provided in sunkoshi hydropower station, each of diameter 2.5m and length 76m
supported on saddle.
4.9
Power house
Power house is a multi-storeyed structure consisting
of power generating equipments like
turbine, generator, switchboard, control room, etc. The net head is of 30.5m.
In
sunkoshi hydropower station, three turbine-generator units are provided. Water
from 3 penstock pipe hit
turbine. Control room is provided to manually control the power generation. The type of turbine used is
Francis turbine. It is reaction turbine and is used for medium head hydropower project. In runner water enters
radially and leaves axially so it is
also called “mixed flow turbine”. Major part of available water energy
is converted into kinetic energy at the
entrance to runner and a considerable remaining part is also utilized as pressure energy. Both kinetic and
pressure energy are directly converted
into mechanical energy by turbine runner before generating electrical energy.
Step
up transformer is used to step the produced voltage of 6.3KV to 66KV.
For
control and protection device, there is 10 circuit breaker(3-generator,2-power transfer,2-station supply and others 3
for local supply). MOCB(minimum oil circuit beaker)
has been replaced by VCB(Vacuum circuit breaker has been used). Natural air cooling, air forced cooling,water forced cooling
are used as cooling system.
4.10 Tailrace canal
The
function of tailrace canal is to discharge the water from powerhouse to river
safely.
No comments:
Post a Comment